The landfill area is planned for construction of 4 landfill cells.
Only landfill cell no 1 will be constructed.
Landfill cell no 1 is covering approximately 1.6 ha and has an estimated capacity of approximately 50,000 m3 waste.
Landfill cell no 2 is planned to be constructed on top of landfill cell no1, by constructing a new embankment on top of the existing embankment. It is estimated that the landfill cell no 2 will have a capacity of approximately 50,000 m3
Landfill cell no 3 and 4 is planned to be constructed next to landfill cell no 1, south of the existing landfill cell.